Chapman Construction Group Awarded and Underway with Installation of 800MW Vineyard Wind 1 Project’s Electrical Service Platform

Massachusetts subcontractor managing multiple union construction trades for Tier 1 EPC Contractors Semco Maritime and Bladt Industries; Developer: Avangrid Copenhagen Infrastructure Partners; Owner: Vineyard Wind, LLC

March 14, 2024 – Sandwich, MA – Chapman Construction Group, Inc. (CCGI), based in Sandwich, MA, has been awarded and is underway with construction operations associated with the completion of offshore construction, installation and commissioning of the 800MW Vineyard Wind 1 project’s electrical service platform (ESP). The wind farm will be located approximately 14 miles southeast of Martha’s Vineyard and 35 miles off the Cape Cod peninsula. CCGI is working as a labor consultant and subcontractor with Tier 1 EPCI contractors Semco Maritime and Bladt Industries in the construction of the substation. The electrical service platform will provide electrical power generated from the Vineyard Wind project, which will be comprised of an array of 62 wind turbine generators to be installed on monopiles in water depths ranging from 121 to 181 feet in the Atlantic Ocean.

Once the electrical service platform is fully constructed and installed, two submarine export cables will transport the electricity to export cable landing points on Cape Cod, in the town of Barnstable, Massachusetts and will connect to a Vineyard Wind onshore substation in Hyannis and then interconnect with an existing, adjacent Eversource substation.

The wind energy project’s 3,200-ton electrical service platform was transported via ship to the offshore Vineyard Wind 1 site from Denmark, where the headquarters of EPC partners Semco Maritime and Bladt Industries are located.

Chapman Construction Group is employing a multi-skilled union workforce consisting of Electricians, Iron Workers, Carpenters, Painters, and Laborers for the project in a unique Project Labor Agreement (PLA) between the Southeastern Building Trades and Vineyard Wind 1 developer Avangrid Copenhagen Infrastructure Partners. The composite crew is working as a team in completion of the electrical service platform. In the project’s construction labor agreement, crews agreed to work across jurisdictional lines. CCGI is managing multiple crews consisting of various union tradespeople working 7 days, 12 hours per day. Each crew is working on a two weeks on/ two weeks off schedule through project completion. Crews are transported by boat from the New Bedford port terminal to the Vineyard Wind site, and live in ship quarters.

Chapman Construction Group’s project team is headed by CCGI principal Vicki Chapman and Dianne Smith.

Due to the offshore location and the size of the turbines, CCGI crews and all trades workers have received Global Wind Operation (GWO) Training, consisting of rescue from heights, water safety, CPR, and Helicopter Underwater Escape Training (HUET) to be able to be transported by helicopter. SPRAT (Ropes Access) training is also required of the trade workers. A rigorous physical exam is also a part of the initial qualification for working offshore.

Onshore construction and staging operations for Vineyard Wind are taking place at the New Bedford Marine Commerce Terminal Facility.

Vineyard Wind 1 is the first utility-scale offshore wind energy project being developed in the United States. With an 800MW capacity, Vineyard Wind 1 is expected to meet the electrical demands of more than 400,000 homes and businesses in Massachusetts. It will generate enough wind power to prevent the emission of more than 1.6 million tons of carbon dioxide every year, the equivalent to withdrawing 325,000 vehicles from the roads. During the life of the project, a projected 3,700 million dollars will be saved in energy costs in New England.

The wind farm will create 3,600 full-time equivalent jobs and under the PLA at least 500 of the jobs created during the construction phase of the project are guaranteed to be filled by local union workers. The PLA includes high hiring targets for women and various groups facing racial discrimination in the US. Vineyard Wind 1 will meet or exceed hiring goals.

Offshore construction of the electrical service platform began in early July 2023.

Chapman Construction Group, Inc. is a WBE, DBE, and Veteran-owned electrical contracting and general contracting company based in Sandwich, Massachusetts. A member of the National Electrical Contractors Association, the company has extensive experience in construction of environmentally sensitive electrical infrastructure projects throughout Cape Cod, Greater Boston, and eastern Massachusetts.

https://www.prnewswire.com/news-releases/chapman-construction-group-awarded-and-underway-with-installation-of-800mw-vineyard-wind-1-projects-electrical-service-platform-302089495.html

Chapman Construction Group Completes Keolis / MBTA North Station Signal System Upgrade Project, Boston, MA

Sandwich, MA – Chapman Construction Group, Inc. (CCGI), a NECA Boston Chapter electrical contractor based in Sandwich, MA, recently completed electrical installations integral to the Keolis / MBTA North Station Terminal Area Signal System Improvement Project.

CCGI’s project scope entailed installation and testing of signal cabling for six new electrical signal house bungalows.  General Foreman and Project Manager John O’Connell headed Chapman’s IBEW Local 103 electrical crew.  Signal house installations and system testing were completed in September 2022.

The upgraded, state-of-the-art MBTA signal system controls the movement of trains coming in and out of North Station. The project will improve the efficiency, safety, reliability, and resiliency of MBTA Commuter Rail and Amtrak trains serviced by the North Station Terminal.  The comprehensive North Station Terminal Signal System Improvement project is scheduled for completion in August 2023.

Chapman Construction Group, a WBE, VBE and DBE contractor, served as a subcontractor to the Keolis project’s primary electrical contractor, Fischbach and Moore.

CCGI Completes Keolis/MBTA North Station Project
High-Profile, January 24, 2023

Photo Captions:
The North Station’s new signal houses are a key component of the MBTA’s new state-of-the-art signal system project, which will control movement and enhance reliability of MBTA and Amtrak trains in and out of North Station.

CCGI in Progress with MBTA Green Line Extension Project

October 5, 2021 – Boston, MA – Chapman Construction Group (CCGI) is in progress with electrical work integral to the MBTA Green Line Extension project. Serving as a subcontractor to GLX Constructors, CCGI’s multifaceted scope has comprised installation of temporary power, duct banks and wiring cable along 7 miles of track from Somerville to Medford, as well as the installation of stray current for bridges. The NECA contractor is managing an electrical crew ranging upwards o 33 IBEW Local 103 electricians. Project operations on the GLX commenced 2018. The project extends Boston’s Green Line to Somerville and Medford and is scheduled for completion in 2022.

Chapman Construction Group Awarded Town of Barnstable’s CWMP Phase 1 Pump Station Project

September 29, 2021 – Barnstable, MA – Infrastructure work in the first phase construction of the Town of Barnstable’s Comprehensive Wastewater Management Plan (CWMP) is underway with the Strawberry Hill Sewer Expansion project. This phase entails construction of the first pump station that will be required in the CWMP.

NECA Boston member, Chapman Construction Group, Inc. (CCGI), based in Sandwich, MA and working as the electrical subcontractor to general contractor, CC Construction, has been awarded the electrical work associated with the new submersible wastewater treatment pump station. Ir will be constructed at the junction of Strawberry Hill Road and Craigville Beach Road. CCGI’s electrical project scope entails the installation of the pump station’s main electrical service, generator, automatic transfer switch enclosures, variable frequency drives, control systems, and all electrical wiring.

Barnstable’s CWMP is a town-wide plan designed to protect Barnstable’s coastal waters, ponds and drinking waters by managing wastewater nutrient pollution and nutrient population in embayments. The project is being constructed in coordination with the Vineyard Wind 1 project. The first phase of the Barnstable CWMP project began in September and is targeted for completion in 2023.

“The installation of pump stations and related water treatment facility systems requires hands-on knowledge and experience with electrical installations that power their operation as well as the integrated control systems,” said Vicki Chapman, president of Chapman Construction.“CCGI is proud to partner with CC Construction and the Town of Barnstable in a project that is of critical importance to the CWMP, the town’s waterways and coastal waters, and Barnstable residents.”